The Hydraulic Machinery Laboratory of IWHR
Time: 2019-07-02 | Hits:

The Hydraulic Machinery Laboratory of IWHR is an independent laboratory. It also is an important part of “Central of hydraulic equipment test for hydropower station”, CNCA. There are three universal high accuracy test rigs for model hydraulic machinery in it, and can be used for the test and research of water turbine, pump and pump turbine. The three test rigs are equipped with high accuracy calibration system, high performance data acquisition and processing system, PLC control system. The measuring accuracy of experimental parameter and the operating stability satisfy the the requirements of related codes of IEC and GB.

Main operation domain

1) Conventionality test: Efficiency test, Cavitation test, Runaway speed test, Pressure fluctuation test, Winter-Kennedv test, etc.

2) Forces characteristic test:  Axial thrust test, Radial thrust test, Guide vane torque test and Runner blade torque test (Kaplan turbine).

3) Four quadrants test for pump-turbine.

4) Flow pattern observation and flow field measurement for hydraulic machinery.

5) Besides upwards functions, TP3 test rig is designed for the performance test of turbine and pump -turbine in sand-water two-phase flow condition (sediment content 0~200 kg/m3).

Mostly Parameters of test rigs

TP1

TP2

TP3

Maximum test head

Hm=150m

Hm=20m

(Hm=80m)

Hm=60m

Test discharge range

0~2.2m3/s

0~1.6m3/s

0~1.0m3/s

Dynamometer

Pe=540KW

Pe=300KW

Pe=300KW

Speed of dynamometer range

0~2600r/min

0~3000r/min

0~3000r/min

Main pump

24SA-10

(Two pumps)

32SA-19

(20SH-9)

28SA-10A

DC motor of main pump

N=724 KW×2

N=593 KW

N=593 KW

Speed of main pump

0~1200

0~1200

0~1200

Model runner diameter range

250mm~500mm

250mm~500mm

250mm~500mm

The highest test head can achieve 150m, and the maximum flow is 2.2m3/s.the total error of model efficiency test of the test rig is less than 0.2 %.

Research domain

·Key problem research for hydraulic machinery;

·Computational analysis of intensity and fatigue of hydraulic machinery;

·Application of hydraulic optimization and analysis of internal flow;

·Flow field display technique of hydraulic machinery;

·Model test and acceptance test;

·Research of cavitation, abrasion mechanism and anti-cavitation, anti-abrasion;

·Measurement and control technique of fluctuation;

·Hydraulic vibration stability of hydraulic machinery.

Main outstanding achievement

National momentous projects participated in:

Model turbine contrastive check test of Three Gorges (right bank);

Model turbine contrastive check test of JinPingⅠ;

Model turbine contrastive check test of JinPingⅡ;

Model turbine contrastive check test of XiLuoDu turbine;

Model turbine contrastive check test of XiangJiaBa turbine;

Model check test for GeZhouBa turbine alteration;

Model check and accept test of HeKou bulb turbine, GanSu;

International cooperative projects:

Model check and accept test of NanLi turbine, Laos;

Model turbine contrastive check test of MuRuo turbine, Malaysia;

Model test for research of KHE BO turbine, Vietnam;

Research projects:

Model test for research of ShuangPai turbine;

Model test for research of 500m head pump-turbine;

Model test for hydraulic design and stability research of BaiHeTan 1000KW turbine.